As-built schedule

as-built schedule

[¦az ¦bilt ¦skej·əl]
(industrial engineering)
The final schedule for a project, reflecting the actual scope, actual completion dates, actual duration of the specified activities, and start dates.

As-built schedule

The final project schedule that depicts the start and completion date, duration, costs, and consumed resources for each activity.
References in periodicals archive ?
Dated final as-built schedule, time file and daily work reports.
A general contractor typically requires access to as-built schedule information to control and manage construction projects.
In Taiwan, there currently exists a multitude of practice problems regarding updating an as-built schedule at the jobsite in Taiwan (Lin 2009).
The proposed approach is to enhance onsite updating of the as-built schedule integrated with BIM models for visual schedule management.
The 4D simulation approach is different from the BIM-based as-built schedule updating system, for which there have only been a few studies.
If the general contractor wants to utilize the commerce BIM software for the application of as-built schedule management, most 4D simulation functionality is incapable of meeting the requirement of updating the as-built schedule management in practice.
Because I've seen so many disputes that could be streamlined or avoided altogether with an accurate as-built schedule, I wanted to provide all project managers with that capability in DailyLog," explained Hoshino.
If the activity was not involved in the analysis scenario, the details of the activity would be inherited from the as-planned schedule, the as-built schedule, or the previous analysis scenario.
Because the EN, EC, and NE delays either impacted the as-planned schedule or occurred in the as-built schedule, computer-based schedule delay analysis methods should deal with these delays based on the adopted process-based and mathematical-model schedule delay analysis methods.
The anticipated completion time in the as-planned schedule was 23 days and the anticipated completion time in the as-built schedule was 35 days.
Depending on the requirement of the adopted process-based and mathematical-model schedule delay analysis methods, the data preparation involves collecting and organizing various schedule documents, for example, as-planned and as-built schedules.
1996) and isolated collapsed but-for (termed as ICBF) (Yang, Yin 2009) methods, the as-planned and as-built schedules were the basic documents, while the revised schedules that represented the identified delay events were additional documents.