Change order


Also found in: Financial, Acronyms, Wikipedia.

Change order

A written order to the contractor signed by the owner and architect or engineer, issued after the execution of a contract, authorizing a change in the work or an adjustment in the contract sum or contract time.

change order

A written order to the contractor signed by the owner and the architect, issued after the execution of the contract, authorizing a change in the work or an adjustment in the contract sum or the contract time as originally defined by the contract documents; may add to, subtract from, or vary the scope of work. A change order may be signed by the architect alone (provided he has written authority from the owner for such procedure and that a copy of such written authority is furnished to the contractor upon request), or by the contractor if he agrees to the adjustment in the contract sum or the contract time.
References in periodicals archive ?
But to date, we have never had a job that did not have change orders, despite the client declaring they will not have any.
The owners waived any requirement for written change orders by repeatedly disregarding the requirement.
Change orders can delay project completion, decrease productivity, increase project costs, hamper procurement, trigger lengthy and complex verification procedures, and stall final account releases and retention payments.
At a minimum, any proposed change order should clearly define and itemize the additional scope of work and document the corresponding costs required to perform that work.
Reece stated the change order would not interfere with the road being built because of the time restrictions in the original contract with Hill Brothers.
Elements of proof for a cumulative impact claim are: (a) a significantly large number of changes; (b) the changes impact on productivity (performance time and efficiency); (c) the impact flows from the synergy of the number and scope of changes; (d) the contractor was unable at time of pricing each change order or directive to foresee the ripple-type effect of the multiplicity of changes; and (e) the contractor did not knowingly waive the right to assert cumulative impact claims when negotiating changes.
Technically, they are right and the School Department business office is following the book by denying the change order.
Secondly, the City will streamline the processing of change orders to reduce the time-frame from the current average of 300 days to an average of 150 days.
And it eliminates some of the risk I face if there's more to the change order than appears at first glance.
getting control of change orders is even more important, because handling customer changes above the standard allowances set in the initial contract is the lifeblood of the custom home business.
Nineteen change orders later and 60 percent over budget, this remodeling has taken a physical and spiritual toll.
For example: Does the roofing project include the replacement of underlayment sheathing, is there an allowance for it, or will it be a change order at the end of the job because the contractor specifically excluded it from his contract?