Encyclopedia

As-built schedule

as-built schedule

[¦az ¦bilt ¦skej·əl]
(industrial engineering)
The final schedule for a project, reflecting the actual scope, actual completion dates, actual duration of the specified activities, and start dates.
McGraw-Hill Dictionary of Scientific & Technical Terms, 6E, Copyright © 2003 by The McGraw-Hill Companies, Inc.

As-built schedule

The final project schedule that depicts the start and completion date, duration, costs, and consumed resources for each activity.
Illustrated Dictionary of Architecture Copyright © 2012, 2002, 1998 by The McGraw-Hill Companies, Inc. All rights reserved
References in periodicals archive
A general contractor typically requires access to as-built schedule information to control and manage construction projects.
In Taiwan, there currently exists a multitude of practice problems regarding updating an as-built schedule at the jobsite in Taiwan (Lin 2009).
The proposed approach is to enhance onsite updating of the as-built schedule integrated with BIM models for visual schedule management.
The 4D simulation approach is different from the BIM-based as-built schedule updating system, for which there have only been a few studies.
If the general contractor wants to utilize the commerce BIM software for the application of as-built schedule management, most 4D simulation functionality is incapable of meeting the requirement of updating the as-built schedule management in practice.
To remedy the problems in the visual updating of the as-built schedule, this study presents the novel ConBIM-SM system to visually update the as-built schedule information for construction project participants.
If the activity was not involved in the analysis scenario, the details of the activity would be inherited from the as-planned schedule, the as-built schedule, or the previous analysis scenario.
Because the EN, EC, and NE delays either impacted the as-planned schedule or occurred in the as-built schedule, computer-based schedule delay analysis methods should deal with these delays based on the adopted process-based and mathematical-model schedule delay analysis methods.
The anticipated completion time in the as-planned schedule was 23 days and the anticipated completion time in the as-built schedule was 35 days.
Kartam (1999) (1) Maintaining effective documents; (2) Analyzing project documents; (3) Analyzing the original schedule; (4) Analyzing project resources utilization; (5) Developing as-built schedule; (6) Identifying delay disruption periods; (7) Analyzing impact of specific issues; (8) Identifying concurrent delays; (9) Applying the contemporaneous period analysis technique; (10) Analyzing the claim; (11) Summarizing various analyses; and (12) Conducting effective meetings.
Depending on the requirement of the adopted process-based and mathematical-model schedule delay analysis methods, the data preparation involves collecting and organizing various schedule documents, for example, as-planned and as-built schedules. The other information process is delay analysis.
Copyright © 2003-2025 Farlex, Inc Disclaimer
All content on this website, including dictionary, thesaurus, literature, geography, and other reference data is for informational purposes only. This information should not be considered complete, up to date, and is not intended to be used in place of a visit, consultation, or advice of a legal, medical, or any other professional.