As-built schedule

as-built schedule

[¦az ¦bilt ¦skej·əl]
(industrial engineering)
The final schedule for a project, reflecting the actual scope, actual completion dates, actual duration of the specified activities, and start dates.

As-built schedule

The final project schedule that depicts the start and completion date, duration, costs, and consumed resources for each activity.
References in periodicals archive ?
The package will include the following: A) Dated final as-built schedule, time file and daily work reports.
A general contractor typically requires access to as-built schedule information to control and manage construction projects.
In Taiwan, there currently exists a multitude of practice problems regarding updating an as-built schedule at the jobsite in Taiwan (Lin 2009).
The proposed approach is to enhance onsite updating of the as-built schedule integrated with BIM models for visual schedule management.
The 4D simulation approach is different from the BIM-based as-built schedule updating system, for which there have only been a few studies.
If the general contractor wants to utilize the commerce BIM software for the application of as-built schedule management, most 4D simulation functionality is incapable of meeting the requirement of updating the as-built schedule management in practice.
To remedy the problems in the visual updating of the as-built schedule, this study presents the novel ConBIM-SM system to visually update the as-built schedule information for construction project participants.
If the activity was not involved in the analysis scenario, the details of the activity would be inherited from the as-planned schedule, the as-built schedule, or the previous analysis scenario.
Because the EN, EC, and NE delays either impacted the as-planned schedule or occurred in the as-built schedule, computer-based schedule delay analysis methods should deal with these delays based on the adopted process-based and mathematical-model schedule delay analysis methods.
The anticipated completion time in the as-planned schedule was 23 days and the anticipated completion time in the as-built schedule was 35 days.
Kartam (1999) (1) Maintaining effective documents; (2) Analyzing project documents; (3) Analyzing the original schedule; (4) Analyzing project resources utilization; (5) Developing as-built schedule; (6) Identifying delay disruption periods; (7) Analyzing impact of specific issues; (8) Identifying concurrent delays; (9) Applying the contemporaneous period analysis technique; (10) Analyzing the claim; (11) Summarizing various analyses; and (12) Conducting effective meetings.
Depending on the requirement of the adopted process-based and mathematical-model schedule delay analysis methods, the data preparation involves collecting and organizing various schedule documents, for example, as-planned and as-built schedules. The other information process is delay analysis.