Bored pile

Bored pile

A pile formed by pouring concrete into a hole in the ground, usually containing some steel reinforcing, as opposed to a pre-cast pile driven into the ground with a pile driver.

cast-in-place pile

A concrete pile which is concreted either with a casing or without a casing at its permanent location, as opposed to a precast concrete pile. cast-in-situ concrete Same as cast-in-place concrete.
References in periodicals archive ?
The complex work involved the installation of bored pile foundation with piles extending to depths of up to 25 metres in deep sea.
95 m bored pile foundation noise barriers, mainly reinforced concrete pile and bored pile foundations length about 2 km, height 2.
7 m hb 2, Hb 3 and hb 4, - 48 m baugrubenverbau carrier screed wall, Berlin shoring, - 169 m ordnance investigation - deep sounding, - 1 930 m bore bored pile diam.
4) section 1 5 st excavation dug as overlapped bored pile wall, Depth up to 14 m, Including waterproof underwater concrete sole and buoyancy control measures: Approximately 850 m pipe jacking dn 1600 by means of full cutting machine (mix-shield), Approximately 35 m pipe jacking dn 400 by means of full cutting machine and rinsing conveyor, Approximately 54 m open installation dn 1200 sb, Approximately 45 m open laying dn 400 sb, Approximately 195 m open installation dn 200/300 pcs, Approximately 400 m 3 reinforced concrete c35 / 45 wu, Approximately 60 t rebar 500 s, Approximately 1 500 m 2 formwork sb2, Approximately 1 200 m 2 surface restoration.
Prior information notice without call for competition: B31 new stockach-berlingen, Ba iib - earthworks and roadworks km 14 + 900 - 15 + 960 1) short description: Earthmoving, Road construction, Bored pile walls, Guards, Signage, Markings 2) common procurement vocabulary (cpv) 45233100 3) quantity or scope: Earth movement approx.
New construction of a single-track railway overpass (e) as flat-ground half-frame made of reinforced concrete and dismantling of the existing e, Expansion of the railway cross section south of the e on about 20 m in length with retaining wall as a tangential bored pile wall.
Contract notice: permanent bored pile slope protection.
The solution adopted involved installation of deep bored piles together with a reinforced earth bund to stabilise the landslip and maintain the original development site.
234 t, Reinforcement in situ concrete bored piles approx.
general description of the scope of services: approximately 11 000 m 3 earthworks; approximately 1 000 m of exploratory drilling (ordnance); approximately 425 m bored piles diam.
2 600 m 3 dismantling reinforced concrete construction, Deliver and install 2 300 t of sheet piling 210 st microverpress piles, 90 pcs reinforced concrete bored piles, Manufacture 4 000 m 3 reinforced concrete structure, Approximately 300 m dismantling / new construction track system incl.
Repository, deep foundation of the abutments by means of bored piles under limited height (28 pieces) in the Bille, production of sheet pile boxes for the production abutment in the Bille.